Earnings Release
EX-99.1 2 hnrg-20260810xex99d1.htm EX-99.1 EXHIBIT 99.1 Hallador Reports Q2 2026 Results; Gas Project Budget Reduced Below $800 Million - Turtle Creek COD Expedited to the Second Half of 2028 - - Contracted Forward Sales Reach $2.4 Billion at the Segment Level - - Management to Host Conference Call Today at 5:00 p.m. ET - TERRE HAUTE, Ind., August 10, 2026 – Hallador Energy Company (Nasdaq: HNRG) (“Hallador” or the “Company”) today reported its financial and operating results for the second quarter ended June 30, 2026. The Company is also providing an update on the continued advancement of its Merom natural gas generation project, now formally named Turtle Creek Gas (“Turtle Creek”), including progress on equipment procurement, financing and interconnection. “Since our strategic update in June, we have made significant progress across key elements of the Turtle Creek project,...